The following tests are to carried out in a distribution board.
Electrical panel board testing procedure. Refer appendix a form 06. Following are the procedure for thermography testing of electrical panels. The procedure for the inspection testing of circuit breakers and switches is beyond the scope of this guide as each type and voltage class has its own procedure. Where applicable testing of circuit breakers generally include.
Some electrical panel test procedures for ensuring the effectiveness of the different elements in the panel and their joint operation are the following. Earth fault loop impedance test earth leakage test for lv distribution board shall be done recorded in prescribed format. Between transformers and mdb s. Ideally this is normal operating load.
Subject panel shall be externally examined before opening or removing any protective covers to determine the possible presence of unsafe conditions. There are 3 cases to be considered. Conduct electrical tests on circuit breakers in accordance with ansi neta section 7. Answer added by faisal shabir shabir ahmad project engineer national for electrical panel boards ksa jeddah 4 years ago continuity test polarity test 2 5 kv test functional test.
The different relay types relay generation and specific. Case 1 is only interconnecting cable between upstream and downstream panels e g. Mounted in the panel using the scheme. Panel to be tested shall be energized and under adequate load.
Refer appendix b test circuit of insulation test. Carry out 500v megger test for phase to earth neutral to earth phase to neutral and phase to phase to measure the insulation resistance with all breakers in on positions. As a main protection element the testing of the relay performance and settings is always included in any panel test. All reading will be recorded in qc 06 quality assurance test report megger.
Inspection test and measurement procedures for lv and mv up to 36kv switchgears on photo eaton cutler hammer magnum ds switchgear inspection and transformer testing for mv switchgear similar considerations apply although more extensive checks on protective devices circuit breaker oil vacuum bottle contact distances are required as. Check the operation of the indicating devices voltmeters protective devices etc.